Case Study

Siemens Healthcare

  Location:  Southampton General Hospital

  Value of Works:  £1,130,000

  Tender & Design Period:  24 Weeks

  Time on Site:  18 Weeks

Purpose of the Project

>span class=”larger”>Installation of 2 magnetic resonance imaging (MRI) systems designed by Siemens Healthcare Systems for imaging of Neurological patients.

The MR systems are 1.5T and 3.0T versions. This installation is part of the much larger Siemens MES project for the imaging department.

Works Undertaken on Site

  • Demolition of existing internal area
  • Construction works, including partitioning, flooring, ceilings and decorations.
  • RF works
  • Electrical works
  • Mechanical works

Challenges

  • Undertaking the works in an existing area within a busy department within a very limited timescale.