  Location:  Hartlepool

  Value of Works:  £490,000

  Tender & Design Period:  32 weeks

  Time on Site:  14 weeks

Purpose of the Project

Replacement of the current Siemens Healthineers MRI scanner.

Works also included refurbishment of the existing rooms reception and office, forming a new w/c and upgrade to the changing and prep areas.

Works Undertaken on Site

  • Construction works.
  • RF works.
  • Electrical works
  • Mechanical works

Challenges

  • Working alongside of an active mobile MRU unit and Mortuary which were in use 24/7.